Description:
Ongoing Projects
Description: Administrative building surrounded by security fence with a sewage treatment plant, water storage and pumping station along with Fire Station.
Description: New Construction Works of the Factory including , Execution Works, Structural Beams Works, Blocking Works, Plastering Works, Tiling Works, Road Pads Works, and all Finishing Work , all Electro-Mechanical Works.
Description: A ONGOING CONSTRUCTION OFFICE BUILDING OF 42,000 M2 WHERE IN STRUCTURAL GLAZING FOR CURTAIN WALLS WAS USED FOR THE FIRST TIME IN OMAN.
Description: Upgrading of existing signalized intersections into wide roundabouts, Construction of six flyovers J7 to J12, Construction of seven footbridges F2 to F8, Renovation and maintenance of Al Ghouse networks and roads paving between intersections and Construction of new services (ITS, Telephone, Fresh water, etc.)
Description: Engineering, Procurement, Construction and Commissioning of the Effluent
Treatment Facilities in Duqm Water Refineries. The facilities are designed to treat
808 m3 of effluent in MAA and 1000 m3 in MAB.
14 Pre- Stressed concrete Structures, 17 Buildings, 57 Steel Tanks 2 Cooling Towers,
5 Chillers, 244 Pumps and 215 Various Mechanical Equipments 2 Substations with 11 KV
incomers, 19 transformers, 11KV & 3.3 KV switchgears Fully Automated plant